1.
Refinish the roof; strip, clean, waterproof and paint
reason... anything leaks through roof fix before ceiling upholstery
need to wait for a week of sunshine...
2.
Upholster ceiling
reason... no mess on finished walls or floors
all re-wiring should be done before wall upholstery
3.
Upholster wall panels
reason... no mess on finished floors
4.
Finish all internal building/modifications
reason... no mess on finished floors
not in way of upholstery
seal all holes in floor
5.
Steam clean engine/under carriage
reason... anything leaks through floor repair
6.
Lay wood and carpet floors
reason... easy access before final install
7.
Final install Seats, TV, sound system, desk
computer station, heat lamps,
Outside paint job
New tires, Smog, engine tune up